Pre-Construction
Coordination: Our Project Management staff will work with you from the very earliest stages
of the project in order to gain a complete understanding of your project scope,
and then will apply our knowledge and experience to make your project a reality.
We will assist in selection of alternates for everything from the structural
design to the materials used to provide you the best product at the best price.
This process is often referred to as value engineering, but it is best done
during the initial definition and design of the project so that the other team
members only have to do their job once. In other words, we will help you achieve the highest value
for your budget, the first time.
Project
Budget: By
combining the information we gain
during the pre-design of the project, we can accurately provide a construction
budget that is both financially feasible and attainable during construction.
This budget is re-examined at key points during design with feedback to all
parties regarding the cost impact of various options. We realize the importance
of staying on budget and the importance of understanding, during this critical
time, the possible cost impact of various decisions.
Construction
Services: When
building multi-family projects, one must keep many factors in mind. Construction
speed is critical to minimizing construction period soft costs, but one must not
sacrifice quality, structure, conformance with applicable safety codes or,
especially, cost. We accomplish all
these through a careful plan that is designed to allow the project construction
to “flow” in an apparently effortless manner. A visit to a Tofel Construction multi-family project will result in an easy recognition of this
factor. Visitors will see a clean site and will easily recognize the order of
the work. The “flow” is accomplished through several key factors and many
much more subtle ones. The keys are:
Subcontractors:
When a job flows, all contractors on the job make money, and that is the
incentive to keep the flow going. One must use subcontractors who are
experienced in multi-family construction and can provide properly trained
personnel.
Schedules:
Schedules
are reduced to their simplest form: Units per day. All workers can understand
this simple directive: they will complete a certain number of units per day,
they will be following a specific trade, and they have to be complete, because
other workers will be following them. As long as they understand this and
completely understand their scope of work, the project can flow.
Prototype
Units:
This is one of the most important steps, and involves all people
associated with the job. Simply stated, at the earliest possible time, the first
units of each floor plan are built, and the following is accomplished: electric
boxes are nailed into position and are labeled as to receptacle, switch, TV,
telephone, or data; all cabinets, door swings and light fixtures are drawn on
the floor. Then all the subcontractor trades meet and discuss the specifics of
how they will install their equipment, where it will go, and what space they
need. All conflicts are resolved at this stage, including required modifications
to framing (e.g., to accommodate HVAC ducts and plenums). Then the owners and
property managers walk through the units to examine for the first time the
interiors of the units. If changes are required, they can be made during this
early construction period when the cost is either very low or nothing. In
this way, all parties know what is expected at the outset and costly, time
delaying changes can be minimized later in the project.
|